Performance in use of completed buildings
Contents |
[edit] Introduction
Generally, performance in use assessments do not begin until 6 to 12 months after occupation, as operations may not be properly established before then, and the development will not have operated in all seasons.
Performance in use assessments should then be part of a continuous, ongoing process.
An assessment of performance in use generally includes an evaluation of two aspects of a development:
[edit] Business objectives
An evaluation of business objectives might include:
- The achievement of business case objectives.
- Whole-life costs and benefits against those forecast (including an assessment of capital costs vs running costs).
- Whether the project continues to comply with the current business strategy.
- Whether operations have improved as a result of the development.
- The resilience of the development and business to ongoing or likely change.
- Business and user satisfaction (including staff and user retention and motivation).
[edit] Design evaluation
An evaluation of design might include:
- The effectiveness of space planning.
- Aesthetic quality.
- The standards of lighting, the acoustic environment, ventilation, temperature and humidity.
- Air-pollution and air quality.
- User comfort.
- Maintenance and occupancy costs.
- Defects.
- The balance between capital and running costs.
- An assessment of whether the development is being operated as designed (including assessment of user controlled systems).
- Environmental and energy consumption in use. NB: Regular evaluation of energy consumption is mandatory for certain types of buildings under the Energy Performance of Buildings (Certificates and Inspections) (England and Wales) Regulations). See the article on energy certificates for more information.
[edit] Assessment
The assessment should compare findings to the original targets set out in business case (the original targets may need to be updated to reflect changes to the project brief during the design process as well as wider changes such as inflation). It should also compare findings to other projects and industry standards and compare the outcome of the project with the position had the project not taken place.
A report should be prepared that identifies issues, recommends remedies, and makes recommendations for improvements in performance both for the development being assessed and for future projects.
[edit] Related articles on Designing Buildings Wiki
- BREEAM.
- Building performance evaluation.
- Building performance metrics.
- Building use studies (BUS).
- Closing the gap between design and as-built performance.
- OGC Gateway Review 5: Operations review & benefits realisation (or benefits evaluation).
- Performance.
- Performance gap.
- Performance of exemplar buildings in use: Bridging the performance gap FB 78.
- Post occupancy evaluation (repeats some of the text in this article).
- Post project review.
- Soft landings.
- Track record.
Featured articles and news
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.